PROJECT SCOPE:
The project involves replacement of the existing curbside operation with modified saw tooth berths in an island configuration. The new layout will also include curbside layover space which is currently unavailable during peak hours.
PROJECT COST:
Approximately $7.7 million
SCHEDULE:
Anticipated completion – Winter 2014
BENEFITS:
Improved vehicular ground transportation at the south side of the facility.
PERMITS:
ACOE Permit No. NAN-2012-00355
NJDEP Permit No. 0900-09-0005.4 FHA 120001
NJDEP Permit No. 0900-09-0005.4 FHA 120002
NJDEP Permit No. 0900-09-0005.4 CDT120001
NJDEP Permit No. PI ID #583462 Auth. Discharge
HEPSCD 251 ID Code #212-H-3003
NJMC #12-174
|